| Award | RENOVATION AND EXPANSION OF ENGINE COMPANY 63- BOROUGH OF THE BRONX | Design and Construction | Kario Construction Corp. | $5.7M | Competitive Sealed Bids | Apr 1, 2011 | 8502011FI0001C |
| Solicitation | CONSTRUCTION OF STORM SEWERS AND APPURTENANCES IN 182ND STREET BETWEEN HILLSIDE AVENUE AND 90TH AVENUE - BOROUGH OF QUEENS | Design and Construction | - | - | Competitive Sealed Bids | Apr 1, 2011 | 85011B0114 |
| Solicitation | IMPROVEMENT OF INTERSECTIONS IN HYLAN BOULEVARD - BOROUGH OF STATEN ISLAND | Design and Construction | - | - | Competitive Sealed Bids | Apr 1, 2011 | 85011B0106 |
| Award | RECONSTRUCTION OF COLLAPSED OF OTHERWISE DEFECTIVE SANITARY, STORM AND COMBINED VITRIFIED CLAY PIPE SEWERS- BOROUGH OF BROOKLYN | Design and Construction | Namow Inc. | $4.3M | Competitive Sealed Bids | Mar 31, 2011 | 8502010SE0021C |
| Solicitation | RECONSTRUCTION OF COLLAPSED OR OTHERWISE DEFECTIVE SANITARY, COMBINED OR STORM SEWERS, FORCE MAINS, DRAINAGE FACILITIES AND APPURTENANCES ON AN EMERGENCY BASIS IN ALL BOROUGHS OF THE CITY OF NEW YORK | Design and Construction | - | - | Request for Qualifications | Mar 28, 2011 | 8502011SE0031C |
| Solicitation | RECONSTRUCTION AND REPLACEMENT OF BROKEN WATER MAINS ON AN EMERGENCY BASIS, CITYWIDE | Design and Construction | - | - | Request for Qualifications | Mar 28, 2011 | 8502011WM008C |
| Award | TAKING OF LAND BORINGS IN THE BOROUGHS OF BROOKLYN AND QUEENS | Design and Construction | AQUIFER DRILLING and TESTING, INC. | $1.8M | Competitive Sealed Bids | Mar 25, 2011 | 8502010PW0001C |
| Solicitation | FORT GREENE HEALTH CENTER BASEMENT RENOVATION/HVAC UPGRADE | Design and Construction | - | - | Competitive Sealed Bids | Mar 23, 2011 | 85011B0104 |
| Solicitation | RECONSTRUCTION OF CHURCH AVENUE FROM FLATBUSH AVE. TO ROGERS AVE. - BOROUGH OF BROOKLYN | Design and Construction | - | - | Competitive Sealed Bids | Mar 21, 2011 | 85011B0103 |
| Solicitation | RECONSTRUCTION OF CONCRETE, STEEL FACED AND GRANITE CURBS AND REPAIR/RESTORE AFFECTED SIDEWALK AND ROADWAY PAVEMENT AS NECESSARY - CITYWIDE | Design and Construction | - | - | Competitive Sealed Bids | Mar 21, 2011 | 85011B0102 |
| Solicitation | RECONSTRUCTION OF JACKIE ROBINSON PARKWAY RETAINING WALL - BOROUGH OF QUEENS | Design and Construction | - | - | Competitive Sealed Bids | Mar 21, 2011 | 85011B0107 |
| Solicitation | CONSTRUCTION OF DONGAN AVENUE FROM BROADWAY TO 88TH STREET - BOROUGH OF QUEENS | Design and Construction | - | - | Competitive Sealed Bids | Mar 21, 2011 | 85011B0105 |
| Award | RECONSTRUCTION OF COLLAPSED OF OTHERWISE DEFECTIVE SANITARY, STORM AND COMBINED VITRIFIED CLAY PIPE SEWERS IN VARIOUS LOCATIONS BOROUGH OF BROOKLYN | Design and Construction | Perfetto Enterprises Company, Inc. | $4.3M | Competitive Sealed Bids | Mar 16, 2011 | 8502010SE0022C |
| Solicitation | KEW GARDENS HILLS LIBRARY RENOVATION AND EXPANSION, BOROUGH OF QUEENS | Design and Construction | - | - | Competitive Sealed Bids | Mar 14, 2011 | 85011B0084 |
| Solicitation | LNCM10DCH, NEW DATA CENTER/HEISKELL, BOROUGH OF MANHATTAN | Design and Construction | - | - | Sole Source | Mar 10, 2011 | 8502011LN0002P |
| Solicitation | REHABILITATION OF COOPER AVENUE RETAINING WALL INCLUDING CURB, SIDEWALK, PAVEMENT RESURFACING, STREET LIGHTING, AND TRAFFIC WORK, BOROUGH OF QUEENS | Design and Construction | - | - | Competitive Sealed Bids | Mar 9, 2011 | 85011B0101 |
| Solicitation | RQ_A AND E, ENGINEERING REQUIREMENTS CONTRACT FOR HVAC, FIRE PROTECTION, ELECTRICAL AND PLUMBING WORK, CITYWIDE | Design and Construction | - | - | Competitive Sealed Proposals | Mar 8, 2011 | 8502011VP0010P-14P |
| Intent to Award | CRO-312OS, DESIGN SERVICES AND SERVICES DURING CONSTRUCTION FOR THE CROTON WATER FILTRATION PLANT-VAN CORTLANDT PARK, BRONX | Design and Construction | - | - | Negotiated Acquisition | Mar 7, 2011 | 8502011PW0015P |
| Solicitation | FLUSHING TOWN HALL GARDEN AND PORTICO RENOVATION-BOROUGH OF QUEENS | Design and Construction | - | - | Competitive Sealed Bids | Mar 7, 2011 | 85011B0063 |
| Award | INSTALLATION OF SIDEWALK, ADJACENT CURBS, HYDRANT FENDERS AND RESTORATION OF HYDRANT CUTS IN VARIOUS LOCATIONS- CITYWIDE | Design and Construction | JREM Construction Corp. | $971K | Competitive Sealed Bids | Mar 7, 2011 | 8502010WM0013C |
| Solicitation | CORRECTION: RESIDENT ENGINEERING INSPECTION SERVICES | Design and Construction | - | - | Competitive Sealed Proposals | Mar 7, 2011 | 8502011HW0038P |
| Solicitation | LQD122-CL, QUEENS CENTRAL LIBRARY-REPLACEMENT OF ROOF, FIRE ALARM, AND EJECTOR PUMP, BOROUGH OF QUEENS | Design and Construction | - | - | Sole Source | Mar 4, 2011 | 8502011LQ0003P |
| Solicitation | RECONSTRUCTION OF FORDHAM KINGSBRIDGE PEDESTRIAN IMPROVEMENTS AND RECONSTRUCTION OF BRYAN PARK - BOROUGH OF THE BRONX | Design and Construction | - | - | Competitive Sealed Bids | Mar 1, 2011 | 85011B0088 |
| Solicitation | RESIDENT ENGINEERING INSPECTION SERVICES | Design and Construction | - | - | Competitive Sealed Proposals | Feb 28, 2011 | 8502011VP0032P-38P |
| Award | CONSTRUCTION OF COMBINED SEWERS AND APPURTENANCES IN 26TH AVENUE BETWEEN 154TH STREET AND 157TH STREET- BOROUGH OF QUEENS | Design and Construction | C.A.C Industries Inc. | $1.5M | Competitive Sealed Bids | Feb 23, 2011 | 8502010SE0020C |
| Award | RECONSTRUCTION OF COLLAPSED OF OTHERWISE DEFECTIVE SANITARY, STORM AND COMBINED VITRIFIED CLAY PIPE SEWERS, BOROUGH OF STATEN ISLAND | Design and Construction | Perfetto Enterprises Company, Inc. | $3.9M | Competitive Sealed Bids | Feb 23, 2011 | 8502010SE0030C |
| Award | RECONSTRUCTION OF COLLAPSED OR OTHERWISE DEFECTIVE SANITARY, STORM AND COMBINED VITRIFIED CLAY PIPE SEWERS IN VARIOUS LOCATIONS- BOROUGH OF QUEENS | Design and Construction | Maspeth Supply Co. Inc. | $4.5M | Competitive Sealed Bids | Feb 23, 2011 | 8502010SE0020C |
| Solicitation | CONSTRUCTION OF STORM SEWERS AND APPURTENANCES IN ELVIRA AVENUE BETWEEN HICKSVILLE ROAD AND OAK DRIVE, ETC. - BOROUGH OF QUEENS | Design and Construction | - | - | Competitive Sealed Bids | Feb 22, 2011 | 85011B0086 |
| Solicitation | SE-809, RESIDENT ENGINEERING INSPECTION SERVICES FOR THE INSTALLATION OF STORM AND SANITARY SEWERS ALONG THE WHITESTONE EXPRESSWAY SERVICE ROAD, BOROUGH OF QUEENS | Design and Construction | - | - | Competitive Sealed Proposals | Feb 22, 2011 | 8502011SE0022P |
| Solicitation | RECONSTRUCTION OF CONNER STREET BULKHEAD - BOROUGH OF THE BRONX | Design and Construction | - | - | Competitive Sealed Bids | Feb 22, 2011 | 85011B0082 |
| Solicitation | CONSTRUCTION OF STORM SEWERS AND APPURTENANCES IN 72ND AVENUE BETWEEN 71ST ROAD AND LITTLE NECK PKWY - BOROUGH OF QUEENS | Design and Construction | - | - | Competitive Sealed Bids | Feb 18, 2011 | 85011B0093 |
| Award | THE STATEN ISLAND MUSEUM RENOVATION OF BUILDING A AT SNUG HARBOR | Design and Construction | C and L Contracting Corp. | $15.0M | Competitive Sealed Bids | Feb 17, 2011 | 8502010PV0009C |
| Solicitation | CONSTRUCTION OF SANITARY AND STORM SEWERS AND APPURTENANCES IN 119TH AVENUE BETWEEN 198TH AND 199TH STREETS - QUEENS | Design and Construction | - | - | Competitive Sealed Bids | Feb 17, 2011 | 85011B0095 |
| Solicitation | CONSTRUCTION OF SANITARY AND STORM SEWERS AND APPURTENANCES IN 200TH STREET BETWEEN 118TH AND119TH AVENUES - QUEENS | Design and Construction | - | - | Competitive Sealed Bids | Feb 16, 2011 | 85011B0094 |
| Solicitation | C114NEWRI, A/E DESIGN SERVICES FOR THE NEW RIKERS ISLAND 1,500 BED ADMISSIONS FACILITY | Design and Construction | - | - | Competitive Sealed Bids | Feb 16, 2011 | 8502011CR0002P |
| Award | CONSTRUCTION OF SANITARY AND STORM SEWERS IN 2ND COURT- OCEANVIEW AVENUE AND BROADWALK AVENUE, ETC.- BOROUGH OF STATEN ISLAND | Design and Construction | Perfetto Enterprises Company, Inc. | $1.8M | Competitive Sealed Bids | Feb 15, 2011 | 8502010SE0002C |
| Solicitation | HELP 1 FAMILY RESIDENCE SITE UPGRADE, BOROUGH OF BROOKLYN | Design and Construction | - | - | Competitive Sealed Bids | Feb 14, 2011 | 85011B0081 |
| Solicitation | INSTALLATION OF HIGH PRIORITY PEDESTRIAN SAFETY SIDEWALKS, ADJACENT CURBS AND PEDESTRIAN RAMPS AS NECESSARY I N VARIOUS LOCATIONS - CITYWIDE | Design and Construction | - | - | Competitive Sealed Bids | Feb 11, 2011 | 85011B0097 |
| Solicitation | HWCRQ02S, SEVEN REQUIREMENTS CONTRACTS FOR RESIDENT ENGINEERING INSPECTION SERVICES FOR SMALL INFRASTRUCTURE PROJECTS, CITYWIDE | Design and Construction | - | - | Competitive Sealed Proposals | Feb 11, 2011 | 8502011VP0015P-21P |
| Solicitation | CONSTRUCTION OF STORM SEWERS AND APPURTENANCES IN METROPOLITAN AVENUE BETWEEN 80TH STREET AND COOPER STREET - QUEENS | Design and Construction | - | - | Competitive Sealed Bids | Feb 10, 2011 | 85011B0085 |
| Solicitation | CONSTRUCTION OF SANITARY AND STORM SEWERS AND APPURTENANCES IN ONEIDA AVENUE, ETC. - BOROUGH OF STATEN ISLAND | Design and Construction | - | - | Competitive Sealed Bids | Feb 9, 2011 | 85011B0078 |
| Solicitation | CONSTRUCTION OF WILLOUGHBY PLAZA ALONG WILLOUGHBY STREET BETWEEN PEARL STREET AND ADAMS STREET - BROOKLYN | Design and Construction | - | - | Competitive Sealed Bids | Feb 9, 2011 | 85011B0083 |
| Solicitation | CONSTRUCTION OF SANITARY AND STORM SEWERS AND APPURTENANCES IN 58TH AVENUE BETWEEN 187TH ST. AND 188TH ST. - QUEENS | Design and Construction | - | - | Competitive Sealed Bids | Feb 8, 2011 | 85011B0071 |
| Solicitation | CONSTRUCTION OF STORM SEWERS AND APPURTENANCES IN 58TH AVENUE BETWEEN 146TH ST. AND 150TH ST. - QUEENS | Design and Construction | - | - | Competitive Sealed Bids | Feb 8, 2011 | 85011B0075 |
| Solicitation | CONSTRUCTION OF COMBINED SEWERS AND APPURTENANCES IN 55TH STREET BETWEEN 12TH AVE. AND NEW UTRECHT AVE. - BROOKLYN | Design and Construction | - | - | Competitive Sealed Bids | Feb 8, 2011 | 85011B0080 |
| Award | CLEANING, TELEVISION INSPECTION AND DIGITAL AUDIO-VISUAL RECORDING OF SEWERS AT UNKNOWN LOCATIONS ON AS NEEDED BASIS- CITYWIDE | Design and Construction | National Water Main cleaning Company | $1.4M | Competitive Sealed Bids | Feb 7, 2011 | 8502010SE0041C |
| Award | EMERGENCY REHABILITATION OF SANITARY AND COMBINED SEWERS BY USING SHOTCRETE METHOD IN VARIOUS LOCATIONS- CITYWIDE | Design and Construction | En- Tech Corp. | $5.5M | Competitive Sealed Bids | Feb 7, 2011 | 8502010SE0025C |
| Award | INSTALLATION OF SIDEWALK, ADJACENT CURBS, HYDRANT FENDERS AND RESTORATION OF HYDRANT CUTS- CITYWIDE | Design and Construction | Perfetto Enterprises Company | $1.8M | Competitive Sealed Bids | Feb 7, 2011 | 8502010WM0001C |
| Award | RECONSTRUCTION OF PALISADES AVENUE RETAINING WALL- BOROUGH OF THE BRONX | Design and Construction | New York Concrete Corp. | $3.6M | Competitive Sealed Bids | Feb 7, 2011 | 8502010HW0056C |
| Award | INSTALLATION OF WATER MAINS IN BROOKVILLE BLVD. AREA- BOROUGH OF QUEENS | Design and Construction | CLEMENTE BROTHERS CONTRACTING CORP. | $7.1M | Competitive Sealed Bids | Feb 4, 2011 | 8502008WM0008C |